Case Study - North Berwick Harbour Stop Log Handling Crane
Client: East Lothian Council
Requirement: Replacement stop log crane installation as part of harbour refurbishments
Site Problems:
Works carried out as part of an extensive refurbishment programme.
Difficult access required specialist craneage.
Marine environment
(See Youtube: Storm Havoc video click link left)

Solution:
The old manuallly operated derrick crane replaced with a new electrically powered free standing swing jib crane.
Marine grade paint finish
360 degree rotation
Control box in IP65 double enclosure.
Plug-in pendant control.
Operations lighting mounted on column.
Two legged chain sling to semi automatic stop logs
lifting beam
Design, manufacture, installation and testing of two complete systems provided by Dales’ in-house crane division.
Click on drawing for larger view
Contact 0161 230 2292 to discover how we can solve your handling problems